Dairy Technologies Corporation (DairyTech) toll manufactures processed cheese in Imus, Cavite under a customer’s own label, and can run a customer’s own formulation. This page covers the three packaging routes, what you must supply for a custom formulation, the minimum order, delivery scheduling, and how long the development process takes.
Does DairyTech offer toll manufacturing and private label?
Yes. DairyTech toll manufactures processed cheese under your own label and product code using our existing packaging, printed by inkjet. We can also run your own formulation, and private label using your own desired packaging is available subject to a thorough discussion with top management. Start the conversation: irenellem@dairytechnologiescorp.com.
- Your label and product code on our existing packaging
- Your own formulation accepted with the required inputs
- Your own packaging discussed with top management
- Formulation development handled by our R&D team
What must I provide to run my own formulation?
Four inputs before we can decide: your product pre-mix, the dry matter percentage for the computation of condensate, the needed water and coconut oil, and the processing requirements in terms of machine settings. Without those we cannot commit to a formulation run. Send your inputs and we will assess feasibility: irenellem@dairytechnologiescorp.com.
- Product pre-mix
- Dry matter percentage for condensate computation
- Required water and coconut oil quantities
- Processing requirements, meaning machine settings
What is the minimum order for toll manufacturing?
One shift production day. That is approximately 180 cases of 2kg pack size, with an allowance of plus or minus 10 percent overrun or underrun. We cannot hold your order for more than 15 days depending on quantity, so the delivery schedule must be stated clearly in the purchase order. Plan your run: irenellem@dairytechnologiescorp.com.
- Minimum — one shift production day
- Approximately 180 cases of 2kg pack size
- Plus or minus 10 percent overrun or underrun allowed
- Cannot hold orders beyond 15 days depending on quantity
How long does developing a custom cheese take?
Plan for the full sequence: ideation and needs assessment at open time, base configuration one week, outsourcing one month, testing one to six months, sampling one week, shelf life study six months including trundling test, batch trial machine run one week to ten days, then customer approval, and validation runs at 30, 60 and 120 cases. Discuss your timeline: irenellem@dairytechnologiescorp.com.
- Base configuration — 1 week; outsourcing — 1 month
- Testing — 1 to 6 months; sampling — 1 week
- Shelf life study — 6 months including trundling test
- Validation runs at 30, 60 and 120 cases, then steady run
Request a sample, specification sheet or quotation
Send your requirement, monthly volume and delivery area to irenellem@dairytechnologiescorp.com, or use the Dairy Technologies Corporation contact page. Full product and specification reference: DairyTech processed cheese supply. Related: Processed Cheese Manufacturer in the Philippines — Dairy Technologies Corporation · Cheese Minimum Order Quantity, Pack Sizes and Lead Time — Philippines · Cheese Supplier Certificate Requirements for Philippine Buyers.